|
| Year |
Period |
Description |
Period covered by |
Funding $$ |
|
| 2006 |
Summer |
Initial Funding |
¦
| |
| 2007 |
Spring |
Funding Distributed |
¦ |
|
| 2007 |
September |
"Kickoff" Meeting |
¦ |
(NRL) |
| 2007 |
Late Fall |
System Requirements Review |
__v__ |
US $3.6 M |
|
| 2008 |
Late Fall |
LWA1 & Preliminary Design |
¦ |
|
| 2009 |
Spring |
Site Dedication |
__v__ |
~US $7M |
|
| 2009 |
Summer |
LWA1 & Critical Design Review |
¦ |
|
|
| 2009 |
|
LWA1 & Initial Construction |
¦ |
|
| 2010 |
|
LWA2-4 Construction |
¦ |
|
| 2011 |
|
LWA5-10 Construction |
__v__ |
~US $33M |
| |
| 2012 |
|
LWIA(16 stations over 200 km) |
|
|
| 2014 |
|
LWA core (i.e., short baselines) |
|
|
| 2016 |
|
53 stations incl. 400 km baseline(s) |
|
|
| |
|
|
|
|